Nebraska Department of Environmental Quality
Pay For Performance
Site Progress Summary


Site Name:White Star Oil
UG# 022291-KM-1100
Posting Date:09/05/2003
Bid Submittal Deadline:08/29/2003
Contractor Selected:SCS Engineers
Bid Price:$560,000.00
Methodology:SVE/AS
Time of Contract:60 Months
.
Contract Type:COC and Free Product
.
Contract Start Date:01/08/2004
.
Milestones Achieved
1.
Start up08/05/2004
2.
25% Reduction02/07/2006
3.
50% Reduction02/07/2006
4.
75% Reduction02/07/2006
5.
SSTLs or No Free Product
6.
One Year Monitoring Start Date
7.
Held SSTLs or No FPNo
8.
Equipment Removal/Site Restoration/ Final Payment
.
Warranty Period (if needed)
Date Warranty Period Started01/08/2009
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP
.
Comments:
The site met the free product cleanup but did not meet the dissolved cleanup levels at the end of the Contract.
Department Contacts: Phil Hargis and David Chambers at (402) 471-3150

For a complete copy of the file, please follow the copying instructions on NDEQ’s PFP web site.



Nebraska Department of Environmental Quality
1200 "N" Street, Suite 400
P.O. Box 98922
Lincoln, Nebraska 68509
(402) 471-2186