Nebraska Department of Environmental Quality
Pay For Performance
Site Progress Summary


Site Name:K&B Transportation
UG# SP# 032091-SM-1410
Posting Date:03/15/2007
Bid Submittal Deadline:06/15/2007
Contractor Selected:Olsson Env.
Bid Price:$182,910.00
Methodology:SVE
Time of Contract:46 Months
.
Contract Type:Free Product
.
Contract Start Date:07/30/2007
.
Milestones Achieved
1.
Start up10/10/2007
2.
25% Reduction04/18/2008
3.
50% Reduction12/15/2008
4.
75% Reduction12/15/2008
5.
SSTLs or No Free Product
6.
One Year Monitoring Start Date
7.
Held SSTLs or No FP
8.
Equipment Removal/Site Restoration/ Final Payment
.
Warranty Period (if needed)
Date Warranty Period Started05/30/2011
Date SSTLs or no FP Achieved
One Year Monitoring Start Date05/30/2012
Held SSTLs or No FPNo
.
Comments:
Free Product remaining at the end of the Contract.
Department Contacts: Phil Hargis and David Chambers at (402) 471-3150

For a complete copy of the file, please follow the copying instructions on NDEQ’s PFP web site.