Nebraska Department of Environmental Quality
Pay For Performance
Site Progress Summary


Site Name:M&H Oil
UG# 072099-CT-1000
Posting Date:04/15/2005
Bid Submittal Deadline:12/03/2004
Contractor Selected:MILCO
Bid Price:$122,944.00
Methodology:Remedial Excavation
Time of Contract:24 Months
.
Contract Type:Free Product
.
Contract Start Date:04/14/2005
.
Milestones Achieved
1.
Start up09/19/2005
2.
25% Reduction02/16/2006
3.
50% Reduction02/16/2006
4.
75% Reduction02/16/2006
5.
SSTLs or No Free Product 02/01/2006
6.
One Year Monitoring Start Date02/01/2006
7.
Held SSTLs or No FPYes
8.
Equipment Removal/Site Restoration/ Final Payment04/16/2007
.
Warranty Period (if needed)
Date Warranty Period Started
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP
.
Comments:
Site Closed
Department Contacts: Phil Hargis and David Chambers at (402) 471-3150

For a complete copy of the file, please follow the copying instructions on NDEQ’s PFP web site.



Nebraska Department of Environmental Quality
1200 "N" Street, Suite 400
P.O. Box 98922
Lincoln, Nebraska 68509
(402) 471-2186