Nebraska Department of Environmental Quality
Pay For Performance
Site Progress Summary


Site Name:Bill's Bait & Tackle
UG# 110294-NM-0815
Posting Date:03/10/2006
Bid Submittal Deadline:05/05/2006
Contractor Selected:MILCO
Bid Price:129,300.00
Methodology:Overexcavation
Time of Contract:20 Months
.
Contract Type:COC
.
Contract Start Date:07/25/2006
.
Milestones Achieved
1.
Start up10/24/2006
2.
25% Reduction10/24/2006
3.
50% Reduction10/24/2006
4.
75% Reduction10/24/2006
5.
SSTLs or No Free Product
6.
One Year Monitoring Start Date
7.
Held SSTLs or No FPNo
8.
Equipment Removal/Site Restoration/ Final Payment
.
Warranty Period (if needed)
Date Warranty Period Started03/25/2008
Date SSTLs or no FP Achieved03/02/2010
One Year Monitoring Start Date03/02/2010
Held SSTLs or No FPNo
.
Comments:
Site had one monitor well that did not meet SSTLs at the end of the monitoring period. DEQ will finish the cleanup.
Department Contacts: Phil Hargis and David Chambers at (402) 471-3150

For a complete copy of the file, please follow the copying instructions on NDEQ’s PFP web site.



Nebraska Department of Environmental Quality
1200 "N" Street, Suite 400
P.O. Box 98922
Lincoln, Nebraska 68509
(402) 471-2186