Nebraska Department of Environmental Quality
Pay For Performance
Site Progress Summary
Site Name:
Dannebrog Auto
UG#
092500-QK-1545
Posting Date:
12/21/2010
Bid Submittal Deadline:
03/04/2011
Contractor Selected:
MILCO Env.
Bid Price:
$146,900.00
Methodology:
SVE
Time of Contract:
30 Months
.
Contract Type:
COC
.
Contract Start Date:
05/09/2011
.
Milestones Achieved
1.
Start up
12/14/2011
2.
25% Reduction
06/19/2012
3.
50% Reduction
06/19/2012
4.
75% Reduction
03/06/2013
5.
SSTLs or No Free Product
6.
One Year Monitoring Start Date
7.
Held SSTLs or No FP
8.
Equipment Removal/Site Restoration/ Final Payment
.
Warranty Period
(if needed)
Date Warranty Period Started
11/09/2013
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
11/09/2014
Held SSTLs or No FP
No
.
Comments:
SSTL's not met. Extended warrenty period declined.
Department Contacts:
Phil Hargis and David Chambers at (402) 471-3150
For a complete copy of the file,
please follow the copying instructions on NDEQ’s PFP web site.
DEQ.NE.Gov Home Page
Security, Privacy & Accessibility Policy
Nebraska.gov
Nebraska Department of Environmental Quality
1200 "N" Street, Suite 400
P.O. Box 98922
Lincoln, Nebraska 68509
(402) 471-2186