Site Progress Summary


Site Name:Seger Oil
UG# 09297-NEW-1400
Posting Date:05/19/2005
Bid Submittal Deadline:12/03/2004
Contractor Selected:Bluestem Environmental
Bid Price:$189,500.00
Methodology:SVE/AS
Time of Contract:24 Months
.
Contract Type:COC
.
Contract Start Date:05/18/2005
.
Milestones Achieved
1.
Start up10/11/2005
2.
25% Reduction02/16/2006
3.
50% Reduction02/16/2006
4.
75% Reduction02/16/2006
5.
SSTLs or No Free Product 07/02/2007
6.
One Year Monitoring Start Date07/02/2007
7.
Held SSTLs or No FPYes
8.
Equipment Removal/Site Restoration/ Final Payment12/01/2008
.
Warranty Period (if needed)
Date Warranty Period Started05/18/2007
Date SSTLs or no FP Achieved07/02/2007
One Year Monitoring Start Date07/02/2007
Held SSTLs or No FPYes
.
Comments:
Site met SSTLs and closed
Department Contacts: Phil Hargis and David Chambers at (402) 471-3150

For a complete copy of the file, please follow the copying instructions on NDEQ’s PFP web site.



Nebraska Department of Environmental Quality
1200 "N" Street, Suite 400
P.O. Box 98922
Lincoln, Nebraska 68509
(402) 471-2186