Nebraska Department of Environmental Quality
Pay For Performance
Site Progress Summary


Site Name:Harry's Truck Stop
UG# 020491-SM-1115
Posting Date:03/10/2006
Bid Submittal Deadline:05/05/2006
Contractor Selected:Panhandle Geotechnical
Bid Price:582,256.00
Methodology:SVE/AS
Time of Contract:48 Months
.
Contract Type:COC and Free Product
.
Contract Start Date:07/26/2006
.
Milestones Achieved
1.
Start up02/28/2007
2.
25% Reduction
3.
50% Reduction
4.
75% Reduction
5.
SSTLs or No Free Product
6.
One Year Monitoring Start Date
7.
Held SSTLs or No FP
8.
Equipment Removal/Site Restoration/ Final Payment
.
Warranty Period (if needed)
Date Warranty Period Started
Date SSTLs or no FP Achieved
One Year Monitoring Start Date
Held SSTLs or No FP
.
Comments:
Contract terminated due to significant AST petroleum release one year after Contract start date. Site now RP lead.
Department Contacts: Phil Hargis and David Chambers at (402) 471-3150

For a complete copy of the file, please follow the copying instructions on NDEQ’s PFP web site.



Nebraska Department of Environmental Quality
1200 "N" Street, Suite 400
P.O. Box 98922
Lincoln, Nebraska 68509
(402) 471-2186