Chapter 4 – NEW DISCHARGER AND NEW SOURCE; APPLICATION

001 A new source or new discharger wishing to discharge pollutants into waters of the state must file an NPDES application at the same time as application is made to the Department for a construction permit for a new source, not less than 180 days prior to commencement of discharge.

002 Except as otherwise provided in an applicable new source performance standard, a source is a new source if it meets the definition of new source in this section.
003 A source meeting the requirements of 002 above is a new source only if a new source performance standard is independently applicable to it. If there is no such independently applicable standard, the source is a new discharger.

004 Construction on a site at which an existing source is located results in a modification rather than a new source (or a new discharger) if the construction does not create a new building, structure, facility, or installation meeting the criteria of 002 above but otherwise alters, replaces, or adds to existing process or production equipment.

005 Construction of a new source has commenced if the owner or operator has:

Enabling Legislation: Neb. Rev. Stat. §81-1505

Legal Citation: Title 119, Chapter 4, Nebraska Department of Environmental Quality